Which phase of project management includes the creation of project deliverables?

Prepare for the AVIXA PTG Test. Use flashcards and multiple choice questions with hints and explanations. Boost your confidence for the exam!

The Execution Phase is where the actual work to create project deliverables takes place. During this phase, project teams move from planning to implementation, translating the project plan into tangible outcomes. This is when resources are allocated, tasks are performed, and progress is monitored against project goals.

In the Initiation Phase, the project is defined at a high level, and initial feasibility assessments are conducted, but no deliverables are created during this stage. The Planning Phase focuses on developing detailed plans on how to achieve the project's objectives, including defining tasks, timelines, and resources needed, but again, this does not involve the actual creation of deliverables. The Closing Phase is concerned with finalizing all project activities, delivering completed outputs, and closing out contracts and documentation, rather than the creation of deliverables themselves.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy