What does "scope creep" signify in project management?

Prepare for the AVIXA PTG Test. Use flashcards and multiple choice questions with hints and explanations. Boost your confidence for the exam!

"Scope creep" signifies uncontrolled changes or continuous growth in project scope, which often occurs when the project is underway and can lead to significant challenges in management. This phenomenon arises when new features, tasks, or requirements are added to the project without proper evaluation or control, typically without adjusting the project timeline, resources, or budget to accommodate these changes.

When scope creep occurs, it can result in projects becoming overextended, leading to delays, increased costs, and a potential failure to meet original project objectives. Recognizing and managing scope creep is crucial to keeping a project on track and ensuring that it adheres to its defined goals. This is why the understanding of scope creep is essential in project management practices, particularly within the AVIXA Project Technologies Group, where precise project execution is fundamental.

The other options highlight various aspects of project management but do not accurately reflect the concept of scope creep. For example, drastic reduction in project resources could lead to project failure but is not synonymous with scope creep. Clear and defined project objectives and successful completion of project milestones are indicators of good project management practices but do not address the issue of uncontrolled changes in scope.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy